Six-hour repair job
A repair is expected to take six hours at a $32 loaded labor cost, use $180 in materials and $60 of other direct costs, with a 10% callback allowance and 30% target margin.
Enter these numbers in the calculator above
- Expected labor hours
- 6 hrs
- Loaded labor cost per hour
- $32
- Materials
- $180
- Other direct costs
- $60
- Callback/rework allowance
- 10 %
- Target margin
- 30 %
Recommended flat rate$678.86
The calculator builds the expected cost, adds the selected rework allowance, and then converts that planned cost into a flat customer price at the target margin.